 Pembangunan MRT Jakarta Fase I Capai 97,06 Persen

Phase I MRT Development Has Reached 97.06 Percent

he three percent deficiency is still in progress at the interior and entrance

The progress on the construction of the phase I Jakarta Mass Rapid Transit (MRT) plying Lebak Bulus-HI Roundabout has reached 97.06 percent.

MRT Lebak Bulus-HI Roundabout Operational Socialization Intensified

"The three percent deficiency is still in progress at the interior and entrance," expressed William P. Sabandar, President Director of PT MRT Jakarta, Tuesday (10/30).

By so, he is optimistic that it will operate in accordance with the schedule in March 2019. Because until now the target of operations is still on time.

"In December 2018-February 2019, we will touch operation trial," he stated.

Linked News
Popular News indeks
  1. Jakarta Claims Rp 2.27 T in Public Assets from Developer Obligations

    access_time06-08-2026 remove_red_eye736 personDessy Suciati
  2. New LapakMain Corner Creative Hub Inaugurated at Tunas Muda RPTRA, Kramat Pela

    access_time05-08-2026 remove_red_eye614 personTiyo Surya Sakti
  3. Abdul Muis Building Fire Response Nears Completion, No Fatalities Reported

    access_time08-08-2026 remove_red_eye564 personAldi Geri Lumban Tobing
  4. Jakarta Ensures Public Services Stay Operational After Abdul Muis Building Fire

    access_time08-08-2026 remove_red_eye524 personFakhrizal Fakhri
  5. Thousand Islands Conducts Vehicle Emission Tests on Three Islands

    access_time07-08-2026 remove_red_eye500 personAnita Karyati